Frequent question: How do I reset a project base point in Revit?

select the layer group, right-click, and click Select Layers Add. In the current drawing, select an object on each layer that you want to add to the group. Press Enter to return to the Layer Properties Manager. select the layer group whose layers you want to replace, right-click, and click Select Layers Replace.

How do you reset base points in Revit?

If you later want to return the project base point to its startup location, do the following:

  1. Select the project base point and unclip it.
  2. Right-click the project base point, and click Move to Startup Location.

How do I delete a project base point in Revit?

You cannot delete the project base point. Project North defines the Y axis of the project base point. To ensure that the project base point does not move inadvertently, you can pin it by selecting the point and clicking Modify tab Modify panel (Pin).

How do you fix coordinates in Revit?

Relocate the Model by Specifying Coordinates

  1. Optional: Display the project base point and the survey point in the current view.
  2. Click Manage tab Project Location panel Coordinates drop-down (Specify Coordinates at Point).
  3. Place the cursor on a reference point of the model. …
  4. Click the reference.
IT IS INTERESTING:  How do I make a specific shape in SketchUp?

How do you reset coordinates in Revit 2020?

Help

  1. Open the host model whose coordinates you want to reset.
  2. Click Manage tab Project Location panel Coordinates drop-down (Reset Shared Coordinates).
  3. Click to close the message indicating the shared coordinates have been reset.

How do I restart Revit?

Try cleanly uninstalling Revit, and then reinstalling: How to Complete a Clean Uninstall of Revit products.

Reset Utility

  1. Download the attached ResetUI Batch utility (ZIP file)
  2. Extract the ZIP file.
  3. Run the BAT file (ResetUI) for the Revit version you want to reset (review included Readme. txt for more details).

How do I set a project base point in Revit 2020?

To select the project base point, move the cursor over the symbol and look at the tooltip or the status bar. If it says Site: Survey Point, press Tab until it says Site: Project Base Point. Click to select the project base point. Drag the project base point to the desired location.

How do you find a project base point in Revit?

Click View tab Graphics panel (Visibility/Graphics). On the Model Categories tab of the Visibility/Graphics dialog, scroll down to Site, and expand it. To display the project base point, select Project Base Point. To display the survey point, select Survey Point.

How do you use project base point?

To make these points visible:

  1. Click View tab > Graphics panel > Visibility/Graphics.
  2. On the Model Categories tab of the Visibility/Graphics dialog, scroll down to Site. …
  3. To display the project base point, select Project Base Point.
  4. To display the survey point, select Survey Point.
IT IS INTERESTING:  What is an example of CAD software often used today?

How do you hide base points in Revit?

To temporarily display the project base point and the survey point in a view, on the View Control Bar click (Reveal Hidden Elements).

How do you unlock visibility graphics in Revit?

The Visibility/Graphics window will be greyed out (as shown above) if its included in the View Properties of the View Template. So make sure you go into the View Template and update the Visibility/Graphics or change settings to not included Visibility/Graphics.

What are the 3 points in Revit?

3- The Spot Coordinates, Spot Elevation and Levels tools set to “Survey Point” don’t actually reference the Survey Point, they refer to the Shared Site Origin. 4- Set the Shared Site Origin and Survey Point early on in the project.

What is the method to georeference a Revit file?

Revit 2018 now has the option to use the Geo-Referenced data from a CAD file that was used to Acquire Coordinate data. When you link and position a Geo-Referenced CAD file, you use the Acquire Coordinates feature in Revit to share coordinate system data between the Revit and CAD file.

How do I set shared coordinates in Revit?

To establish a common coordinate position and then share that position between files, use the Acquire Coordinates tool or the Publish Coordinates tool. Tip: You should derive shared coordinates from only one file. That one file defines the coordinates for all other files that compose the project.