How do you find a project base point in Revit?

To see the base point in your revit model, open a site plan and then the visibility graphics window. Expand the Site Category, then make sure the Project Base Point is set to visible. Next select the project base point in the Revit View, and click on the paperclip icon.

What is a project base point in Revit?

The project base point can be used to establish a reference for measuring distances and positioning objects in relation to the model. … When you first create a Revit model, the project base point is located at the internal origin. When starting a project, decide where in the model the project base point will be placed.

How do you find coordinates in Revit?

Acquire Coordinates

  1. Open the host model.
  2. Link the file from which you want to acquire coordinates. The link can be topography, a DWG or DWF file, or a Revit model.
  3. Click Manage tab Project Location panel Coordinates drop-down (Acquire Coordinates).
  4. Place the cursor on a link, and click.

How do you set a project base point in Revit?

Define the Project Base Point

  1. Open the site plan view or another view that displays it. …
  2. To select the project base point, move the cursor over the symbol and look at the tooltip or the status bar. …
  3. Drag the project base point to the desired location.
IT IS INTERESTING:  How do I add a forming tool in SOLIDWORKS design library?

How do you set a project base point and survey point in Revit?

To make these points visible:

  1. Click View tab > Graphics panel > Visibility/Graphics.
  2. On the Model Categories tab of the Visibility/Graphics dialog, scroll down to Site. …
  3. To display the project base point, select Project Base Point.
  4. To display the survey point, select Survey Point.

What is acquire coordinates in Revit?

Acquire Coordinates. When you acquire coordinates from a linked Revit project, the shared coordinates of the linked project become the shared coordinates of the host project, based on the position of the linked project instance in the host project. There is no change to the host project’s internal coordinates.

How do I reset a project base point in Revit?

If you later want to return the project base point to its startup location, do the following:

  1. Select the project base point and unclip it.
  2. Right-click the project base point, and click Move to Startup Location.

What is the method to georeference a Revit file?

Revit 2018 now has the option to use the Geo-Referenced data from a CAD file that was used to Acquire Coordinate data. When you link and position a Geo-Referenced CAD file, you use the Acquire Coordinates feature in Revit to share coordinate system data between the Revit and CAD file.

What is the difference between survey point and project base point?

Moving an unclipped survey point moves only the survey point relative to the shared coordinate and the project coordinate systems. Project coordinates do not change for the model elements. Shared coordinates do not change for the model elements. Only the shared coordinates of the survey point itself change.

IT IS INTERESTING:  You asked: How do you scale text in AutoCAD?

How do you move project base point more than 10 miles?

If you are wanting to move the project base point to a new location outside of 10 miles from origin

  1. In 2020.2. 1 and earlier: Un-clip base point and use Relocate Project to move project base point.
  2. In 2020.2. 2 and later: Go to Manage > Coordinates > Specify Coordinates at Point.
Special Project