Your question: Can you filter by phase in Revit?

How do you filter a schedule by phase in Revit?

Apply a Phase to a Schedule

  1. In the Project Browser, select the schedule name.
  2. On the Properties palette, under Phasing, select values for the Phase Filter and Phase parameters.
  3. Click Apply.

How do you control phases in Revit?

Create a Phase

  1. Click Manage tab Phasing panel (Phases). The Phasing dialog opens, displaying the Project Phases tab. …
  2. Click the number box adjacent to a phase. Revit selects the entire phase row. …
  3. Insert a phase. …
  4. If desired, click the Name text box of a phase to rename it. …
  5. Click OK.

How do you show all phases in Revit?

To access all Phases options, go to Phases menu in the Manage tab. The first thing you need to do is set the phases you require. RENOVATION PROJECT: In most Revit templates, the basic phases are Existing and New. For most project, this is all you will need.

How do you override phase filters in Revit?

Click the Phase Filters tab. For each filter, specify how you want to display the elements for each phase status (New, Existing, Demolished, and Temporary). For phases that use the graphic override settings, select Overridden. Click OK.

IT IS INTERESTING:  Who can use AutoCAD?

Can you combine schedules in Revit?

You can combine two or more parameters to display in a single cell of a schedule. The values for the combined parameters are separated by a slash or other character you specify.

How do I use temporary phase in Revit?

Go to Manage Tab → Phasing → Graphic Overrides. Here you will see the Phase Graphic Override Settings that you currently have for all model geometry – Existing, Demolished, New and Temporary.

Can you change phase of room in Revit?

Room phases can’t be switched because if you demolish a wall i.e. two rooms become one room. Therefor they can only exist in their own phase, so from that point of view it makes sense the way it is.

How do you merge phases in Revit?

Combine Phases

  1. Click Manage tab Phasing panel (Phases).
  2. Click the number box adjacent to the phase to combine with another phase.
  3. Under Combine with, click Next or Previous.
  4. Click OK.

In the drawing area of the host model, select the linked Revit model. Click Modify | RVT Links tab Properties panel (Type Properties). In the Type Properties dialog, find the Phase Mapping parameter and click Edit. In the Phases dialog, select the appropriate mapping options for each phase, and click OK.

How do you show demolition in Revit?

Demolish Elements

  1. Open the view in which you want to demolish elements.
  2. Click Modify tab Geometry panel (Demolish). The cursor changes to a hammer.
  3. Click the elements to demolish. …
  4. To exit the Demolish tool, click Modify tab Selection panel (Modify).