How do you fix shared coordinates in Revit?
Reset Shared Coordinates
- Open the host model whose coordinates you want to reset.
- Click Manage tab Project Location panel Coordinates drop-down (Reset Shared Coordinates).
- Click to close the message indicating the shared coordinates have been reset.
Which point is associated with the shared coordinate system?
Survey Point (SP – Blue Triangle)
This is the point that stores the universal coordinate system, or a defined global system of the project to which all the project structures will be referred. It shows as a blue triangle. And: It is the origin that Revit will use in case of share coordinates between models.
How do you publish coordinates in Revit?
Publish Coordinates
- Open the host model whose coordinates you want to share with the linked model.
- Click Manage tab Project Location panel Coordinates drop-down (Publish Coordinates).
- Place the cursor on a linked model instance and click.
- Select a named position from the linked model, and click OK.
How do I get shared coordinates?
Acquire Coordinates
- Open the host model.
- Link the file from which you want to acquire coordinates. The link can be topography, a DWG or DWF file, or a Revit model.
- Click Manage tab Project Location panel Coordinates drop-down (Acquire Coordinates).
- Place the cursor on a link, and click.
How do I change shared location in Revit?
Relocate the Model by Specifying Coordinates
- Optional: Display the project base point and the survey point in the current view.
- Click Manage tab Project Location panel Coordinates drop-down (Specify Coordinates at Point).
- Place the cursor on a reference point of the model. …
- Click the reference.
How do I move a linked model in Revit?
In the drawing area, select the linked model instance, right-click, and click one of the following options: Reposition to Project Base Point: Positions the RVT link using the model’s Project Base Point as the insertion point, and aligns it to the Project Base Point in the host model.
How do you align a CAD file in Revit?
To manually align a DWG with a Revit model:
- Open the Revit model.
- Link the DWG: Click Insert tab Link panel (Link CAD).
- Manually move the DWG to the correct place.
- Use ‘Specify Coordinate at a Point,’ and specify the desired coordinate value.
How do you share in Revit?
Enable Worksharing
- Open the project file (RVT) to use as the central model.
- Click Collaborate tab Manage Collaboration panel (Worksets). …
- If desired, rename the worksets.
- In the Worksharing dialog, click OK. …
- In the Worksets dialog, click OK. …
- Click Save As (Project).
How do you use coordinate models in Revit?
When reloaded, the coordination model retains its position and orientation in relation to the Revit model.
- Click Insert tab Link panel (Coordination Model).
- In the dialog, select the coordination model.
- To reload the selected model, click Reload.
What the option acquire coordinates and publish coordinates do in Revit?
When you acquire coordinates from a linked model or file, the coordinates of the linked model establish the shared coordinate system of the host model. When you publish shared coordinates from a host model to a linked model, the linked model is updated with the new coordinates.