Create a Schedule or Quantity

  1. Click View tab Create panel Schedules drop-down Schedule/Quantities.
  2. In the New Schedule dialog, do the following: Select a component from the category list. …
  3. In the Schedule Properties dialog, specify the schedule properties. Select Fields. …
  4. Click OK.

How do I edit a schedule in Revit?

select a cell or column in the schedule body. Click (Insert) on the Columns panel to open the Select Fields dialog, which functions like the Fields tab of the Schedule Properties dialog. Add new schedule fields and adjust the field order as needed.

Do Revit schedules automatically update?

All schedules update automatically when you modify the model. For example, if you move a wall, the square footage updates in a room schedule accordingly. When you change the properties of building components in the model, the associated schedule updates automatically.

How do you find quantity in Revit?

Generate the building part data used for quantification.

  1. Click Quantification tab Buildingbook Extension (Calculate Building Part Quantities).
  2. In the Calculate Building Part Quantities dialog, select a calculation type.
  3. Be sure that you have selected the elements you need for your building part quantities calculation.
IT IS INTERESTING:  How do you draw a spiral staircase in Autocad?

How do I add a total area in a room schedule in Revit?

To create the schedule



On the Fields tab, add the desired fields to the schedule, including the Area field. On the Sorting/Grouping tab, select the Grand Totals check box. On the Formatting tab, select the Area field and select the Calculate Totals check box. Click OK.

Why can’t I edit schedule in Revit?

issue: Some schedule fields in Revit are not editable. Cause: In some instances, schedules created in Revit and viewed in Revit will not be editable. Schedules will be shown correctly, but the column containing the column containing the combined parameter will not be able to be edited.

How do you crop a schedule in Revit?

Split a Schedule on a Sheet

  1. Open the sheet.
  2. Select the schedule on the sheet. …
  3. Click the Z break control. …
  4. To split a section of the schedule further, click the Z break control again. …
  5. To adjust the number of rows in a section of the schedule, drag the blue dot at the bottom of the first section.

How do I create a custom schedule in Revit?

Create a Key Schedule

  1. Click View tab Create panel Schedules drop-down Schedule/Quantities.
  2. In the New Schedule dialog, select the element category for which you want to schedule keys.
  3. Select Schedule keys. …
  4. Click OK.
  5. In the Schedule Properties dialog, add the predefined fields for the style. …
  6. Click OK.

Which control do you select to change a schedule column width Revit?

To adjust the column width, select the schedule. A blue triangle displays to the upper right of each column. Drag a blue triangle to the left or right. Note: If the schedule is split into multiple sections, adjusting the width in one section changes the width in all sections.

IT IS INTERESTING:  Frequent question: How do I change the radius in AutoCAD?

Is there a refresh button in Revit?

The Refresh button can be used to force Ideate Explorer to re-build the element list within the Results pane. There are several situations where this may be needed: Using Activate View from a Sheet, the Results will continue to display the Sheet elements if the Active View is Display option is current until a Refresh.

What are Revit schedules?

A schedule is a tabular display of information, extracted from the properties of the elements in a project. A schedule can list every instance of the type of element you are scheduling, or it can collapse multiple instances onto a single row, based on the schedule’s grouping criteria.

How do I make a wall schedule in Revit?

To create a Wall Schedule:

  1. On the View tab, in the Create panel, click the small arrow below Schedules and choose Schedule/Quantities.
  2. In the Category list, Choose Walls. …
  3. In the Available Fields list, look for the useful fields (i.e. Family and Type, Length etc.). …