Export a Schedule

  1. Open a schedule view.
  2. Click File tab Export Reports Schedule.
  3. In the Export Schedule dialog, specify a name and directory for the schedule, and click Save. …
  4. Under Schedule appearance, select export options: …
  5. Under Output options, specify how you want to display the data in the output file: …
  6. Click OK.

How do I Export multiple schedules from Revit to excel?

What’s the Easiest and Quickest Way to Export Multiple Schedules from Revit?

  1. Download the installer executable. …
  2. Run installer.
  3. Start Revit. …
  4. You will have two new tabs: Case Apps #1 and Case Apps #2.
  5. Click on Case Apps #2 –> Export Schedule.
  6. Chose to either export as separate files or as one file with multiple tabs.

How do I copy a Revit schedule?

Solution:

  1. Open both projects in the same window of Revit.
  2. In the first project, right click on the name of the schedule you want to copy, and choose “Copy to Clipboard”
  3. In the target project, use the Paste command on the Manage ribbon, or type CTRL+V to paste the schedule into the project.

How do I extract data from Revit?

Export Revit Data to a Database

  1. On the Link Revit Model with Database dialog, select MS Access.
  2. Select a recently used connection, or click Select a new connection to create a new connection. If you selected Select a new connection, the Select database dialog displays. Browse to the desired location. …
  3. Click Export.
IT IS INTERESTING:  How do you join two walls in Revit?

How do I Export a CSV file from Revit?

Detailed item information can be generated and exported to CSV files.



Set Up Item Data Export

  1. Click Add-Ins tab Revit Extension for Fabrication panel Fabrication Exports and click Set Up Item Data Export.
  2. In the Export Data Wizard (Item Information) dialog, to Create a New Export format, click Next.

How do I export a sheet from Revit to excel?

Solution:

  1. Go to the Application menu (big R in top left) or the File menu in Revit 2018 and later releases.
  2. Select Export.
  3. Scroll down the list until you come to Reports > Schedule.
  4. This will then export a *. txt file.
  5. Import this *. txt file into Microsoft Excel.

You can include elements from linked models in schedules of model elements (such as walls, floors, and roofs) and in drawing lists. They are not supported for note blocks, view lists, or key schedules.